Need Facility Information or Assistance?

Need help with one of our applications? Need record information about a building or project?  Submit a ticket or give us a call!

FIS Support Line

Call our support line to speak directly with one of our staff!

(517) 353-3434

 

Facility information links

FIT has links to a variety of other sources of facility related information across campus.  Be sure to check it out for more information!

Search the Portal

Recent Articles

JAN17
CP18116 PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP

FIELD: DESCRIPTION FROM: PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP TO: PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP BY: JANDREWS ON: 01/17/2019 AT 01:48 P.M.

Capital Project Updates
JAN16
CP16226 HUBBARD HALL - EXTERIOR MASONRY RESTORATION AND WINDOW REPLACEMENT - PHASE 3

FIELD: STATUS FROM: SUBSTCOMP TO: CLOSED BY: LSENECAL ON: 01/16/2019 AT 04:44 P.M.

Capital Project Updates
JAN14
CP18121 PARKING RAMP 2-AUDITORIUM RD - REPLACE ELEVATOR

FIELD: STATUS FROM: OUTBID TO: RELCON BY: ACOMPEAN ON: 01/14/2019 AT 12:49 P.M.

Capital Project Updates
JAN14
CP18121 PARKING RAMP 2-AUDITORIUM RD - REPLACE ELEVATOR

STATUS CHANGED FROM: OUTBID TO: RELCON BY: ACOMPEAN ON: 01/14/2019 AT 12:49 P.M. Additional Info: Lead Designer: GOTTSCHALK Project Rep: GOTTSCHALK Consultant: Delivery Method: TBD - TO BE...

Capital Projects Released For Construction
JAN3
CP17175 INTERNATIONAL CENTER - RENOVATION TO SUITES 205, 207 AND 211

STATUS CHANGED FROM: IN DES TO: RELCON BY: BCHARLAND ON: 01/03/2019 AT 12:50 P.M. Additional Info: Lead Designer: POSTMAM Project Rep: POSTMAM Consultant: IPF Delivery Method: IPF - IPF...

Capital Projects Released For Construction
DEC2018
CP16196 SEWER DISTRIBUTION - SANITARY AND STORM SEWER - REPAIR ALLOWANCE STUDY

STATUS CHANGED FROM: SUBSTCOMP TO: RELCON BY: LSMITH ON: 12/20/2018 AT 07:08 A.M. Additional Info: Lead Designer: TROTTERM Project Rep: - Consultant: FISHBECK, THOMPSON, CARR & HUBER Delivery...

Capital Projects Released For Construction
DEC2018
CP18164 HANNAH ADMINISTRATION - 4TH FLOOR ALTERATIONS

STATUS CHANGED FROM: IN DES TO: RELCON BY: ACOMPEAN ON: 12/18/2018 AT 04:13 P.M. Additional Info: Lead Designer: MULLENB Project Rep: MULLENB Consultant: Delivery Method: DB - DESIGN BUILD

Capital Projects Released For Construction
DEC2018
CP18104 STEAM DISTRIBUTION - 18-19 MISC MAJOR REPAIRS

STATUS CHANGED FROM: IN DES TO: RELCON BY: ADURHAM ON: 12/13/2018 AT 12:04 P.M. Additional Info: Lead Designer: GARDNERM Project Rep: GARDNERM Consultant: Delivery Method: TBD - TO BE DETERMINED

Capital Projects Released For Construction