Recent Articles

JAN18
CP17186 COWLES HOUSE - ADDITION 3 AND SITE RENOVATIONS

FIELD: DESCRIPTION FROM: 18891855 TO: COWLES HOUSE - ADDITION 3 AND SITE RENOVATIONS BY: ACOMPEAN ON: 01/18/2019 AT 01:21 P.M.

Capital Project Updates
JAN18
CP17186 COWLES HOUSE - ADDITION 3 AND SITE RENOVATIONS

FIELD: DESCRIPTION FROM: COWLES HOUSE - ADDITION 3 AND SITE RENOVATIONS TO: 18891855 BY: ACOMPEAN ON: 01/18/2019 AT 01:19 P.M.

Capital Project Updates
JAN18
CP17044 MSU COLLEGE OF LAW - ALTERATIONS TO ROOMS 200 AND 215-221

FIELD: STATUS FROM: SUBSTCOMP TO: CLOSED BY: LSENECAL ON: 01/18/2019 AT 11:42 A.M.

Capital Project Updates
JAN17
CP18116 PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP

FIELD: DESCRIPTION FROM: PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP TO: PARKING RAMP 5-COMM ARTS - REPAIR CONCRETE AT CATA BUS LOOP BY: JANDREWS ON: 01/17/2019 AT 01:48 P.M.

Capital Project Updates
JAN16
CP16226 HUBBARD HALL - EXTERIOR MASONRY RESTORATION AND WINDOW REPLACEMENT - PHASE 3

FIELD: STATUS FROM: SUBSTCOMP TO: CLOSED BY: LSENECAL ON: 01/16/2019 AT 04:44 P.M.

Capital Project Updates
JAN14
CP18121 PARKING RAMP 2-AUDITORIUM RD - REPLACE ELEVATOR

STATUS CHANGED FROM: OUTBID TO: RELCON BY: ACOMPEAN ON: 01/14/2019 AT 12:49 P.M. Additional Info: Lead Designer: GOTTSCHALK Project Rep: GOTTSCHALK Consultant: Delivery Method: TBD - TO BE...

Capital Projects Released For Construction
JAN3
CP17175 INTERNATIONAL CENTER - RENOVATION TO SUITES 205, 207 AND 211

STATUS CHANGED FROM: IN DES TO: RELCON BY: BCHARLAND ON: 01/03/2019 AT 12:50 P.M. Additional Info: Lead Designer: POSTMAM Project Rep: POSTMAM Consultant: IPF Delivery Method: IPF - IPF...

Capital Projects Released For Construction
DEC2018
CP16196 SEWER DISTRIBUTION - SANITARY AND STORM SEWER - REPAIR ALLOWANCE STUDY

STATUS CHANGED FROM: SUBSTCOMP TO: RELCON BY: LSMITH ON: 12/20/2018 AT 07:08 A.M. Additional Info: Lead Designer: TROTTERM Project Rep: - Consultant: FISHBECK, THOMPSON, CARR & HUBER Delivery...

Capital Projects Released For Construction